AI data centers in Texas could sharply increase air emissions: what the HARC report found and what the owner of a business that relies on cloud AI should take from it
Topics: AI, Small business

Short answer: the Houston Advanced Research Center (HARC) calculated that if every proposed Texas data center connects to the grid at the generation mix expected there, within five years that could wipe out decades of past gains in air quality. In this scenario, soot from power generation would more than triple, reaching its highest level since 2006; smog-forming NOx would rise 136%, nearing 2004 levels; and CO2 would climb 90% above 2025 levels. This is HARC's calculation for one specific scenario, not a certain prediction. The outcome depends heavily on how developers choose to power their data centers: the grid, onsite gas generators, or onsite renewable generation.
What HARC actually calculated
The Verge (author Justine Calma, October 21, 2026) covers a new report from HARC, a research organization based in Texas. The primary source on HARC's own site did not load while I was preparing this piece (it did not respond either directly or through an archive), so what follows relies on The Verge's account, which itself quotes the report and a HARC press release.
The scenario in short: Texas has a huge number of proposed data centers. If all of them connect to the shared grid at the generation mix now expected there, electricity demand would jump sharply, and power-sector emissions with it. For exactly this scenario, "all proposed projects connect to the grid," The Verge gives figures: soot from the power sector would more than triple, NOx would rise 136%, and CO2 would be 90% above 2025 levels. The Verge separately notes that HARC's work also used three different projections for data center energy demand. Whether those three projections are the same thing as the scenario above, or a separate set of calculations, and what figures the projections produce if they differ, cannot be determined from The Verge's account.
HARC director John Hall said in the press release: "There is a good chance that our children and grandchildren will breathe dirtier air than we do. The transportation sector, the state, and other stakeholders have been working for decades to bring these [emissions] numbers down, and that progress is now at risk."
Why the outcome isn't fixed
The outcome isn't fixed, for two reasons. First, many proposed data center projects are speculative and could fall by the wayside: that's how The Verge describes them, citing its own earlier reporting on inflated forecasts for AI electricity demand. Second, where centers do get built, developers have a choice in how to power them, and that choice changes the resulting pollution level substantially:
- If a data center pairs grid power with its own onsite solar or wind generation, NOx emissions could be up to 10 times lower.
- If a developer installs onsite gas generators instead, to avoid waiting for a grid connection (which can take a long time in Texas), the opposite happens: by HARC's calculations, that produces the highest pollution level of all the options.
Texas is currently the largest US data center market by capacity: 26 gigawatts of existing and under-construction infrastructure, according to a JLL report cited by The Verge. By a separate March report from consulting firm Wood Mackenzie, also cited by The Verge, Texas is bracing for four times more proposed onsite-generation data center capacity than any other US state. The Verge notes one more detail: developers often choose less efficient gas turbine technology because it lets them build faster. By the outlet's assessment, that makes the whole data center boom dirtier than it would need to be at a slower pace.
What to take from this if you run a business on AI
A Russian company has no direct stake in Texas air quality, but the story carries two concrete practical takeaways.
If you host a server with a third-party data center or lease colocation (renting space and power for your own equipment inside someone else's data center). Before signing a contract, ask the provider directly: what powers the site's primary and backup capacity, the grid, its own gas generation, or onsite renewables. A good answer names a specific energy source and, if a share figure exists, that share too (for example, "80% grid, 20% our own solar panels"). Generic phrases like "eco-friendly" or "green data center" without a named energy source don't count as an answer: ask for specifics. Get the answer in writing, in the contract, a letter, or the provider's own page about its power supply: that way you'll have a document to point to if the site's terms change later. If a provider can't or won't answer directly, that's itself a useful result: you can treat transparency about power supply as one of your criteria for choosing a site, alongside price and SLA.
If your server sits on your own premises, rather than with a third-party provider. Before buying high-power server hardware, check with your own electricity utility whether the added load from the server and its cooling fits within the capacity limit specified in your current grid connection agreement. This is a checkable fact from your own contract, not a forecast: the answer is either within the limit or it isn't.
If you simply use a ready-made cloud AI subscription, with no server of your own. Every six months, check whether your provider has a public pricing or sustainability page, and read it if it exists. If language about rising energy or infrastructure costs shows up there, that's a reason to ask your provider or reseller in advance whether a subscription price increase is expected, rather than finding out after the fact from your bill. If no such page exists, or no such language appears, you don't need to go looking for it separately: treat that as a neutral result, not a reason for concern.
Bottom line
HARC's report has several possible paths forward, so it isn't a certain prediction of what will happen. The figures above apply to one specific scenario: every proposed project connecting to the grid at the expected generation mix. How that scenario relates to HARC's other calculations can't be determined from The Verge's account. If every proposed Texas data center connects to the grid at the expected generation mix, within five years that could wipe out decades of past gains in air quality. The outcome depends on each developer's choice of power source. For a business that hosts a server with a third-party provider or on its own site, there's a direct practical takeaway: find out in writing what powers your load and on what terms, before signing a contract or buying equipment.
I run a portfolio of AI agent and automation projects for businesses: see examples or write directly about your own project. For another angle on the money behind AI infrastructure, see my piece on banks trying to resell AI data center debt.
Sources
- Justine Calma. Data centers could erase decades of air quality gains. The Verge, 10/21/2026. https://www.theverge.com/ai-artificial-intelligence/1015958/data-center-pollution-rising-report
- Houston Advanced Research Center. Texas Data Center Air Quality (report; the primary source did not load while preparing this piece). https://harcresearch.org/research/texas-data-center-air-quality/
- JLL. North America data centers (data center capacity report, via The Verge). https://www.jll.com/en-us/insights/market-dynamics/north-america-data-centers
- Wood Mackenzie. Newly added US data center capacity slows down considerably in Q4 2025... (press release, published in March; the year is not stated in The Verge's account). https://www.woodmac.com/press-releases/newly-added-us-data-center-capacity-slows-down-considerably-in-q4-2025-as-market-struggles-to-keep-up-with-explosive-demand/